City gives update on street projects

Thu, 06/30/2016 - 6:05 pm

City Manager Mike Smith delivered a report on current and future street projects at the Jacksboro City Council meeting Monday.

Here is his report.

North Knox Street from Live Oak to McConnell Street has been previously milled and stabilized and is scheduled for chip seal in July.

West Union Street from Main Street to North Knox Street has been previously milled and is scheduled for chip seal in July.

North 9th Street from West Belknap to West Live Oak has had water lines replaced. Sewer lines have been spot repaired, camera work completed and are ready for relining. The street has been milled and stabilized. A chip seal is complete. The intersections have been milled and stabilized and are scheduled for chip seal in conjunction with the North Knox Street chip seal project.

West College Street from North 9th to North 1oth has been milled and stabilized. A chip seal is complete. Installation of concrete curb and gutter at the intersection of North 10th Street is scheduled for completion in July.

North 10th Street from West Archer to West College has been milled and stabilized. A chip seal is complete. Installation of concrete curb and gutter at the intersection of West College Street is scheduled for completion in July.

West Street from West Belknap to West Archer has had partial curb and gutter removed and replaced with an approach. It is scheduled to be milled, stabilized and chip sealed in July. The remaining curb, gutter and approach work will be scheduled dependent upon property owner’s plans for renovation of two existing buildings.

To read the complete update, see the July 1 edition of the Herald-Gazette.